How frequently must the rolling operation be performed during testing?

Once

Twice

Minimum of three times

The correct answer is that the rolling operation must be performed a minimum of three times during testing. This requirement is critical because it ensures that the concrete sample is thoroughly and uniformly consolidated before testing. The rolling operation helps to eliminate air pockets, which can lead to inaccuracies in measurements and affect the test results.

By consolidating the concrete sample adequately, you ensure a better representation of how the concrete will behave in the field. This practice is especially important during tests like the slump test or any other procedure requiring consistency in the concrete's density and workability, ensuring that the findings are valid and reliable.

Performing the rolling operation less than three times could result in an insufficiently compacted sample, leading to misleading results that do not accurately reflect the concrete's true properties. This is why the minimum of three times is a standard requirement in the testing protocols.

Get further explanation with Examzify DeepDiveBeta

Four times or more

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy