Question: 1 / 400

How frequently must the rolling operation be performed during testing?

Once

Twice

Minimum of three times

The rolling operation must be performed a minimum of three times during testing to ensure that the results are consistent and reliable. This frequency allows for adequate mixing of the concrete sample, helping to eliminate any variability that may occur from simply taking a single reading or performing just one rolling operation. By rolling the sample multiple times, the technician can help to provide a more accurate representation of the concrete’s characteristics, such as its density and workability. This practice aligns with the standard procedures outlined in ACI guidelines, reinforcing the importance of thoroughness and consistency in concrete testing for achieving valid results.

Get further explanation with Examzify DeepDiveBeta

Four times or more

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy